Corporate Social Responsibility (2010)
TALA HYDROPOWER PLANT
Nu.0.247 m was provided as a financial support to Meritsemo Lhakhang for the installation of Zhung of the statues.
Nu. 4.700 m was provided for the Wang Water Basin Management.
Nu. 1.ooo m was provided for balance clock tower works in Gaeddu College of Business Studies which is in a stage of completion.
CHHUKHA HYDROPOWER PLANT
- Nu.3.000 m was provided for Drubchhen Cermony and Baazagurudungdup to be performed by a minimum of 300 people towards the end of Drubchhen. The cermony was held from 1st May till 11th May.
KURICHHU HYDROPOWER PLANT
- Nu.0.150 m was provided for Annual Mangi Rimdro which was conducted for the wellbeing and the welfare of the community as a whole.